Water Main Improvements on Cedar Street & Walnut Avenue

Key Elements

Berg served as primary construction manager for this Bid-Build project. Approximately 950 feet of existing old water mains, located primarily on two residential streets, were replaced with 8” – 12” ductile iron pipe. In addition, 22 water services and 2 fire hydrants were replaced. The project included laying of new pipe, installation of gate valves, fire hydrants, meters, air relief valves and associated laterals as well as connections to existing systems, chlorination, flushing, pressure testing, and reconstruction of the trench and roadway to final grade. Additionally, 2 existing valves were removed and replaced at the request of the water department. This extra work was tracked and paid on a T&M basis.